Change the World > Darebin Bridge > 2. Darebin Bridge project > 2. History of the Darebin Bridge
2. History of the Darebin Bridge
1989 – User survey showed strong support for bridge
1993 - Lower Darebin Creek concept plan adopted.
1993 - Golf club agrees to allow the trail through.
1995 – BVNews article calls for the bridge to be built
1997 – BVNews reports state funds are solid.
1997 - Boroondara approves plan and funding
1997- Locals object to Tribunal claiming it is a ‘pristine area’. Objection thrown out and permit awarded
1998 – LaTrobe Golf Club refuses to sell land to the trail.
1999 – Boroondara planning approval lapses and is extended
2000 – Minister Thwaites commits to Public Open Space zoning for the trail and bridge
2001 – Boroondara refuses to extend planning approval
2002 – Boroondara endorses Willsmere Park Management Plan and bridge
2002 - Golf Club to “fight tooth and nail” against trail
2004 – Concept design completed by Parks Victoria
2005 – Negotiations completed for two key properties north of Heidelberg Road Bridge
2006 – Premier Bracks announces $2 million funding